Construction Progress of Package G55 – 500kV Transmission Line Project from Nam Dinh 1 Thermal Power Plant to Pho Noi
04/02/2026The construction teams and crews on-site have been working together diligently, working overtime to ensure the completion of their assigned daily workloads, while maintaining schedule adherence, quality, and safety throughout the construction process.
To date, the construction site of Package G55 has completed the foundation works for towers VT180, VT182, VT184, VT185, and VT187 (spread footing type). Towers VT181 and VT188 are currently in the process of steel installation, while towers VT179A, VT183, VT186, VT189, and VT190 are undergoing mass piling works.
Some images from the construction site:
Mr. Dang Hoang An, Chairman of the Members’ Council of EVN, inspects the construction progress of the project.
Pile driving and foundation excavation for tower VT179A under construction.
Backfilling and site preparation for tower erection at VT180 under construction.
Foundation steel installation for tower VT181 under construction.
Foundation inspection prior to grounding installation for tower VT182.
Pile driving for the foundation of tower VT183 under construction.
Backfilling and completion of foundation works for tower VT184 under construction.
Inspection and preparation for the erection of tower VT185.
Pile driving for the foundation of tower VT186 under construction.
Cleaning prior to beam concrete pouring for tower VT187.
Foundation steel installation for tower VT188 under construction.
Pile driving for the foundation of tower VT189 under construction.
Pile driving for the foundation of tower VT190 under construction.
Mass concrete pouring for piles under construction.