Electrical Works – LSP A1 Package – Olefins Plant
-
Investor: LSP Co., Ltd. / Technip Joint Venture
-
Address: Long Son, Ba Ria – Vung Tau
-
Construction Period: 26 months
-
Scope of Work: Supply of materials, installation equipment, and cable inspection for the electrical package
-
Electrical and Equipment Works – LSP C-PP Package
-
Investor: LSP Co., Ltd. / SAMSUNG Engineering
-
Address: Long Son, Ba Ria – Vung Tau
-
Construction Period: 22 months
-
Scope of Work: Supply of materials, installation execution, and cable inspection for the electrical and equipment package
-
Temporary Construction Works – LSP A1 Package – Olefins Plant
-
Investor: LSP Co., Ltd. / Technip Joint Venture
-
Address: Long Son, Ba Ria – Vung Tau
-
Construction Period: 21 months
-
Scope of Work: Design, supply of materials, civil works construction, equipment installation, testing and commissioning for the TCF package